Secretary of State for Defence v Turner Estate Solutions Ltd


Citation: [2014] EWHC 244 (TCC)

In this Arbitration claim the Claimant seeks relief under s.68 of the Arbitration Act 1996 (“the Act”) in relation to a second part award dated 29 July 2013 made by the arbitral tribunal (“the Tribunal”). The arbitration arises under a contract dated 31 March 2003 (“the Contract”) under which the Claimant engaged the Defendant to carry out, amongst other things, the design and construction of a substantial regeneration project involving Core Works. The Contract was a bespoke contract based on a Maximum Price Target Cost (“MPTC”).